Pre-handover (PCI) checklist for a Tarneit volume build

What to check at practical completion in a Tarneit home, room by room, and what builders typically leave for the defects period.

Owner Inspections · Tarneit 3029 · 2026-09-01

In short: Inspect outside, inside and roof space before you sign the handover form. Hand the builder a numbered list, agree fix dates, and reinspect before settlement.

Why PCI matters more in Tarneit

Volume builders in Tarneit run tight programs with rotating trades. Practical completion is the last point where the contract obliges the builder to fix defects before you take the keys. After handover, you rely on the defects liability period and the builder's goodwill.

Outside

Ridge capping and roof tiles, gutter falls and valley outlets, downpipes connected to stormwater, render cracking at control joints, brick staining and mortar gaps, door thresholds, garage floor ponding and site drainage away from the slab.

Inside

Paint and plaster in natural light, cornice joints, doors and windows operating, tile lippage and grout, silicone at wet area junctions, cabinetry alignment, benchtop seals, appliance installation, tapware and drainage.

Roof space and services

Insulation coverage, sarking, exhaust fans ducted to outside, plumbing and electrical penetrations, and solar penetrations sealed.

What to do with the list

Hand the numbered report to your site supervisor, agree a fix date, and book a reinspection before you settle. Do not sign the handover form until the major items are closed.

Written by the Owner Inspections team from inspections carried out in Tarneit. Licensed building practitioners, Building & Plumbing Commission registration CDB-U 53425.

Guides

More pci / handover guides for Tarneit

All guides →

Book a building inspection in Tarneit

Instant online pricing, or talk to the booking team on 1300 471 805.

FAQ

Questions Tarneit owners ask about this

How many defects does a typical Tarneit PCI report list?

Between 40 and 120 items on a standard volume build. Most are finishing defects; a handful are usually worth escalating.

Can I refuse to settle until defects are fixed?

Check your contract. Most Victorian contracts let the builder call practical completion with minor defects outstanding, but you can insist on a documented list and fix dates.

Does this apply outside Tarneit?

The standards apply across Victoria. The local detail here, soil, builders and council process, is specific to Tarneit and the Wyndham growth corridor.

Who can I ask about my own property?

Call 1300 471 805 or use the quote form and add your question in the comments. A licensed inspector will answer.